Paint System Builder Guide
Man Days
Once all of the required fields of a system are entered, you’ll find that the Man Days are populated with the amount of Man Days that each coat of your particular type of system requires.
Man Days refers to how many days that it will take for 1 man to accomplish the task of applying a finish, based on the production rates chosen in the Coats area. Totals will be shown per coat, from 1 to 4 coats, depending on how many coats the system required.
There is also a field, Total Man Days for all coats of the system.